This page maintains additional attributes for expense lines added to a field service order. It displays the extended price calculated for the expense line.
Linking Field Service Orders to Projects and Tasks
Linking a machine to a project and task in a field service agreement links any field service order for that machine to that project. Linking a task to a machine in the field service agreement links that task to a field service order by default but can be overridden.
If a machine is not linked to a project and task in a field service agreement, the field service order can be optionally linked to any project and task during processing.
Processing
Tabs
This page displays header attributes for a field service order. |
|
This page maintains material lines for the FSO. |
|
This page maintains service lines for a field service order. |
|
This page displays and maintains expenses for the FSO. |
|
This page displays and maintains labor lines for the FSO. |
Paging Area
Charge Code |
A code representing an additional charge for customer orders that are not associated with an item record or a customer record. Source: Additional Charges Maintenance in Company Tables. |
Quantity |
The required quantity. |
Reason |
A code representing the reason for this transaction. Source: Reason (SYRSNS) in Company Tables. |
Currency |
A code representing a currency used for monetary exchange. Source: Currency Maintenance (SYCURRS) in System Tables. |
Price |
The unit price times the quantity. |
Overridden Price |
The new extended price. |
AGC |
Item accounting group code. The accounting group code assigned to a record determines the accounts used to create journal entries when Financial Integration Management is processed. Source: Item AGC Maintenance in Company Tables. |
Project |
The project linked to the order. Source: Project Definition Maintenance in Project Definition. If this field service order is linked to a field service agreement using Project Task Linking in Field Service Orders in glovia G2, the project cannot be changed. Otherwise blank and can be manually changed. |
Task |
The task linked to the order line. Source: Project Definition Maintenance in Project Definition. If this field service order is linked to a field service agreement using Project Task Linking in Field Service Orders in glovia G2, the task defaults to the task selected for this machine in the field service agreement. Otherwise blank. Can be manually changed. |
Comments |
This window allows comments to be entered about this line. |
Hyperlinks
Update FSO |
Updates the field service order. |